Skip to main content
Zemerc
CCMSDeliver · Completions, Quality & Handover

Completion, Commissioning & Handover Management System

Certificates are controlled gates supported by completion evidence.

The completion and commissioning lifecycle is governed within one project record, covering systemisation, inspection and test records, punch control, certificate progression and the evidence required for handover.

0
Work areas
0
Controlled registers
0
Report definitions
0
Certificate types
The certificate sequence

Gate release depends on completed deliverables, not a percentage alone.

Six controlled certificate types are configured in a project sequence and then locked. Whether mechanical completion or ready-for-pre-commissioning comes first is project-specific, but the approved sequence does not drift during execution.

Systemisation
Engineering register
Inspection and test
Execution
Punch clearance
Punch list
Mechanical completion
Certificate workspace
Ready for commissioning
Commissioning
Handover
Certificates & handover

Systemisation. Plant is divided into systems and subsystems, with each engineering item registered against one before completion status can be assessed.

Inside CCMS

Every plant object is registered against the controlled templates that govern it

Opening a system shows its plant-hierarchy position, applicable controlled certificate templates, inspection-and-test categories and outstanding punch affecting the next gate.

The CCMS systems register with a system open beside it: the plant hierarchy from area through system to subsystem, the controlled certificate templates that apply to it, and the completion modules showing inspection and test record categories and punch items

Completion is calculated as records achieved against records required, allowing the result to be traced back to its components.

  • Traceable to the applicable revision
    Executed records retain the exact template revision against which they were signed.
  • Category A blocks the applicable gate
    Punch items are counted by category against the system to which they belong rather than aggregated into a single clearance percentage.
  • Dual-party signature
    Contractor and client signatories are recorded on the certificate together with the relevant approval parties.
From systemisation to handover

Outstanding scope reduces at each controlled gate

Each stage reduces outstanding scope, and each reduction is supported by a signed record. Progression is based on evidence rather than planned dates alone.

SystemisationEngineering register

Plant is divided into systems and subsystems, with each engineering item registered against one before completion status can be assessed.

Inspection and testExecution

Category A, B and C inspection and test records are executed against approved template revisions, with check sheets, loop checks and test packs behind them.

Punch clearancePunch list

Punch items are raised and cleared by category. Category A items must be cleared before the gate they block, and counts remain associated with the relevant system.

Mechanical completionCertificate workspace

The first certificate gate is issued against completed deliverables. Project configuration may place ready-for-pre-commissioning first where required.

Ready for commissioningCommissioning

Commissioning proceeds on the systems whose evidence supports it, through site acceptance testing and start-up.

HandoverCertificates & handover

Pre-start-up safety review, ready for start-up and the final handover certificate, with turnover packages and dossiers assembled from the records that produced them.

Capability architecture

Fourteen work areas supported by one governed engineering register

CCMS navigation is organised around the way completions teams work, from engineering registers through execution and handover.

  • Systemisation

    The engineering register provides the authoritative project hierarchy from plant through tag level, supported by line, valve, instrument, cable and loop lists.

    • Areas
    • Systems
    • Subsystems
    • Packages
    • Equipment
    • Tags
    • Line Lists
    • Loops
    • Engineering Register
  • Controlled templates

    Inspection and test records, check sheets and certificate templates are maintained in an approved revision-controlled library so executed records remain traceable to the exact revision used.

    • Template library
    • Approval Workspace
    • Revision management
  • Execution

    Inspection and test records in categories A, B and C, check sheets, loop checks, test packs and the punch list, through pre-commissioning, commissioning, site acceptance testing, start-up and performance tests.

    • ITRs
    • Check sheets
    • Loop Checks
    • Test packs
    • Punch list
    • Precommissioning
    • Commissioning
    • Site acceptance tests
    • Startup
    • Performance Tests
  • Certificates and handover

    A configurable, lockable certificate sequence supports dual-party signatures, phase and area handover certificates, turnover packages and the governing event matrix.

    • Certificate Workspace
    • Stage sequence
    • Phase Handover
    • Area Handover
    • Turnover packages
    • Event Matrix
  • Deliverables and spares

    Documents, drawings, single-line diagrams, piping and instrumentation diagrams, isometrics, vendor documents, calibration certificates, inspection and test plans and as-builts, with spares and interchangeability records beside them.

    • Documents
    • Drawings
    • SLDs
    • P&IDs
    • Isometrics
    • Vendor documents
    • Calibration Certificates
    • Inspection and test plans
    • As-Builts
    • Spares & SPIRs
  • Quality and knowledge

    Technical queries, non-conformance reports, management of change and lessons learned, with preservation, the knowledge platform and the data management workspace supporting them.

    • Technical queries
    • NCRs
    • Management of Change
    • Lessons Learned
    • Preservation
    • Knowledge platform
    • Data management
Systemisation structure

Twenty thousand plant objects linked to applicable controlled templates

Lines, valves, instruments, cables and loops are governed within one engineering register with discipline, area, system and subsystem context. Applicable controlled templates are listed by inspection-and-test category and project revision.

  • Plant, area, system, subsystem, package, equipment and tag within one governed hierarchy
  • Register-backed traceability from each record
  • Temporary systems are maintained separately from permanent systems
Signatory responsibilities

Signatories are recorded against the work they verified

Commissioning engineers, inspectors and authorised signatories work from the same governed records. Certificates retain the people who executed and approved them together with the template revision in force at the time.

  • Project roles for general users, super users and administrators
  • Execution signatories and approval parties recorded on the certificate
  • Barcode and QR scanning so records can be raised where the equipment is located
Progress and reporting

Progress percentages are meaningful because they are derived from governed records

Overall progress, mechanical completion, commissioned equipment, punch clearance and certificate approval are calculated from the underlying records, with planned and actual positions visible together.

CCMS progress view showing overall progress, mechanical completion, commissioned equipment, punch clearance, completed inspection and test records, approved certificates, planned-versus-actual schedule curves, and progress by discipline, system and subsystem
  • Deliverable-driven rather than percentage-driven

    Certificates are issued against completed deliverables. Completion percentage is derived afterwards for reporting and does not itself release a gate.

  • Signed against the applicable revision

    Executed records retain the exact template revision against which they were signed, preserving the applicable rules for later review.

  • Dual-party signature

    Certificates record contractor and client signatories together with the execution and approval parties associated with the certificate.

  • Certificate sequence configured and locked for each project

    The approved order of mechanical completion and ready-for-pre-commissioning is configured once per project and then locked.

Also in CCMS

More of what the application covers

  • Visual progress tracker and three-dimensional facility view
  • Schedule curve comparing planned and actual progress
  • Barcode and QR scanning on site
  • Print and document packs
  • Guided imports and a migration workspace
  • Preservation registers with due dates
  • Eighty-nine governed report definitions
  • Tenant administration with project-specific role controls
CCMS

Review CCMS using one of your systems

Bring one system and its inspection and test records. The demonstration will follow it from systemisation through punch clearance to certificate release, including the applicable template revisions.